Panel Installation
Intricate, architecturally designed houses will obviously take longer as there are often steel beams to be installed which can slow down the panel installation process. Consider the following:
Delivery
The site must have crane access. Access also required for a 13 metre truck and trailer unit. Check with Litecrete if in doubt.
Craneage
Cranes are the most expensive pieces of equipment used during installation and it is important to plan ahead to optimise craneage time. The ground must have sufficient stability to support the weight of the crane/truck.
Typical Installation Methods
The panels sit in a 50 mm deep rebate which has been previously been cast in to the floor slab – see Detail R3(2) on Page 31 in the Litecrete catalogue. The panels sit on concrete footings below the floor level, prior to the floor slab being poured – Detail R3(3) on Page 32.